Capital Campaign

Renovation Details

Exterior Restoration & Repair – $229,628

  • Masonry Restoration – $180,375
  • Entrance Walk Replacement – $180,375
  • Fascia & Trim Repair – $230
  • Gutter & Downspout Replacement – $5,839
  • Exterior Paint & Caulking – $9,400
  • Exterior Signage Replacement – $1,250
  • Window Shutters – $15,200
  • Security – $6,000

Interior Remodeling & Repair – $156,588

  • Kitchen Remodel – $27,513
  • Restroom Remodel – $44,150 + $10,390
  • Refurbish Entry Vestibule – $1,095
  • Repair Stair Balustrade – $5,700
  • Refurbish 2nd & 3rd Floor Corridors – $7,340
  • Replace Sleeping Room Doors – $7,020
  • Miscellaneous Repair – $4,550
    • Plaster Repairs
    • Hazardous Material Testing & Abatement

Mechanical, plumbing, electrical and fire protection work – $304,500

  • HVAC System – $130,000
  • Plumbing System – $75,000
  • Fire Protection System – $90,000
    • On December 23, 2005 the governor of Wisconsin passed an Emergency Rule stating that by the year 2014 all fraternities and sororities associated with the University will need to be equipped with a sprinkler system and updated fire alarm system.
  • Electrical System – $52,500

Project Summary

Exterior restoration and repairs: $229,628
Interior remodeling and repair: $156,588
Mechanical and electrical upgrades: $304,500
Construction subtotal: $690,716
GC overhead and profit: (15%) $103,607
Design contingency: (20%) $158,865
Construction total: $953,188
Design, legal, approvals, etc.: (15%) $142,978

PROJECT COSTS: $1,096,166